FOI release
A30 Carland Cross to Chiverton scheme costs - bat house
Case reference EIR2024/01866
Received 30 December 2024
Published 10 February 2025
Request
Could you please advise the full costs of the bat house recently constructed on the A30 Carland Cross to Chiverton scheme?
Response
Information provided
The total cost of the bat house constructed as part of the A30 Chiverton to Carland Cross scheme was £171,240.85.
Advice and Assistance
More information about the bat house can be found here.