FOI release

Final project cost for the A27 at Arundel

Case reference FOI2024/01359

Received 19 October 2024

Published 18 November 2024

Last amended 13 December 2024

Request

As I understand it there have been a number of figures bandied about as to the final projected project cost for the A27 at Arundel. Could I please ask as an FOI what the final project cost was for the A27 at Arundel?

Response

On 29 July 2024, Richard Holden MP, asked the Secretary of State for Transport, in a written Parliamentary Question, what estimate her Department has made of the potential cost of the A27 Arundel Bypass as well as other schemes on the Strategic Road Network.

On 03 September 2024 Lilian Greenwood MP, the Parliamentary Under-Secretary of State for the Future of Roads, answered that the estimated capital cost of the A27 Arundel Bypass was £630m.

 The full question and response can be found at the link below.

Written questions and answers - Written questions, answers and statements - UK Parliament

Documents

There are no documents for this release.

This is National Highways' response to a freedom of information (FOI) or environmental information regulations (EIR) request.