Major Scheme NEC Option C Pain/Gain share values
Case reference FOI2024/01134
Received 21 September 2024
Published 13 December 2024
Request
Please can you provide the pain/gain share values and percentages used between the National Highways and the Contractor within the NEC Option C contracts utilised by National Highways in the delivery of major highways schemes (£10 m or greater) in the last 3 years.
Response
The main route to markets for operations spend within National Highways is either the Scheme Delivery Framework or the Pavement Delivery Framework. The following contractors share percentages, and the share ranges apply under these frameworks.
Contractor’s share percentage |
||
---|---|---|
Less than |
85% |
0% |
From |
85% to 95% |
25% |
From |
95% to 105% |
50% |
Greater than |
105% |
25% |
Over the last three years, National Highway has delivered 8 operational projects with a value of £10>.
Documents
There are no documents for this release.
This is National Highways' response to a freedom of information (FOI) or environmental information regulations (EIR) request.
You can browse our other responses or make a new FOI request.