FOI release

Major Scheme NEC Option C Pain/Gain share values

Case reference FOI2024/01134

Received 21 September 2024

Published 13 December 2024

Request

Please can you provide the pain/gain share values and percentages used between the National Highways and the Contractor within the NEC Option C contracts utilised by National Highways in the delivery of major highways schemes (£10 m or greater) in the last 3 years.

Response

The main route to markets for operations spend within National Highways is either the Scheme Delivery Framework or the Pavement Delivery Framework. The following contractors share percentages, and the share ranges apply under these frameworks.

Contractor’s share percentage

Less than

85%

0%

From

85% to 95%

25%

From

95% to 105%

50%

Greater than

105%

25%

 

Over the last three years, National Highway has delivered 8 operational projects with a value of £10>.

Documents

There are no documents for this release.

This is National Highways' response to a freedom of information (FOI) or environmental information regulations (EIR) request.

You can browse our other responses or make a new FOI request.