Highways major schemes - cost estimates vs outturn cost

Case reference FOI2025/01539

Received 6 August 2025

Published 18 December 2025

Request

Please provide the following commercial information for the completed major highway infrastructure projects listed below:

1. A14 Cambridge to Huntingdon Improvement

2. A1 Leeming to Barton Improvement

3. M4 Smart Motorway (Junctions 3–12)

4. M6 Toll

5. M25 Widening (Junctions 16–23 and 27–30)

6. A19 Testo’s Roundabout

7. A19 Norton to Wynyard Improvement

8. A1 Coal House to Metrocentre Widening

9. M1 Junctions 6a–10 Widening

10. A2 Bean and Ebbsfleet Junction Improvements

11. A556 Knutsford to Bowdon Dual Carriageway

12. M20 Junction 10a Improvement Scheme

13. M62 Junctions 10–12 Widening

14. A43 Corby Link Road

15. A46 Newark to Widmerpool Improvement

16. A2/A282 Dartford Improvement

17. A3 Hindhead Tunnel

18. M74 Completion Project (Scotland, if applicable under remit)

19. A46 Coventry Junction Improvement

20. A421 Bedford to M1 Dualling

For each project, please provide:

1. The initial approved cost estimate (e.g. Strategic Outline Business Case or Outline Business Case stage)

2. Any revised estimates (e.g. Full Business Case, contract award)

3. The final outturn cost (upon project completion)

4. The dates of each cost estimate and completion

5. A brief explanation (if available) for any significant variance between early estimates and the final outturn cost (e.g. scope changes, inflation, delays, unforeseen events)

Response

Please refer to the attached spreadsheet. Some points to note regarding the provision of the data:

• Robust cost capture began at the start of RP1 (Road Period 1 - 2015-2020).We do not hold the information requested for older schemes.

• Reasons for any cost increase over the lifecycle of a scheme has been tracked from the start of RP2 (Road Period 2 - 2020-2025). Information for schemes prior to this date is not available.

• The A46 Coventry junctions is one scheme to improve two junctions, Binleyand Walsgrave. The data provided is for Binley as Walsgrave has not yet started works. As such the reasons for cost increase on Binley has not been analysed by the team yet.