FOI release

Operation Brock

Case reference FOI2024/00660

Received 27 July 2024

Published 16 May 2025

Last amended 16 May 2025

Request

  • How many times has Operation Brock been activated in 2023, 2022, 2021, 2020 and 2019?

  • How much is the total cost of activating and de-activating Operation Brock during each of the calendar years listed above?

  • What is the longest continuous period of time Operation Brock was implemented for and how many days was it in place before de-activation?

  • If this information has already recently been published - can you please redact and send to me?”

Response

The decision to deploy Operation Brock is not taken lightly and is made jointly between the Kent and Medway Resilience Forum partners – National Highways, Kent Police, Kent County Council, local authorities and the Government – based on several key factors. These include intelligence gathered about emerging situations, traffic modelling and passenger/freight bookings. When Brock is active, all KMRF partners work to return the situation to normal as quickly as possible.

 

As a KMRF partner organisation, National Highways deploys a quick movable barrier on the M20 when a decision to implement Brock is taken. This can be set up overnight and separates traffic into different lanes across both carriageways, allowing us to hold HGV's heading to the Port of Dover and Eurotunnel and to release them in an orderly manner. This keeps the M20 and other local roads open and moving.

 

 

The table below shows data from 2019 up to June 2024.

 

Year

Start Date

End Date

Days Active

Combined Cost to Activate/Deactivate

Cost Comment

2019

24/03/2019

18/04/2019

25

£ 795,000

23km Steel barrier installation & removal Traffic Management set up and labour

2020 / 2021

28/12/2020

28/04/2021

121

£ 250,000

20km full movement of concrete barrier & Traffic Management set up and labour

2021

17/07/2021

01/08/2021

15

£ 250,000

2022

22/03/2022

06/06/2022

76

£ 175,000

Traffic Management set up and labour only. The concrete barrier already in place for the M20 Moveable Barrier Project

2022

11/07/2022

04/09/2022

55

£ 175,000

2022

17/12/2022

07/01/2023

20

£ 175,000

2023

26/05/2023

05/06/2023

10

£ 250,000

20km full movement of concrete barrier & Traffic Management set up and labour

2023

14/07/2023

20/08/2023

40

£ 175,000

Traffic Management set up and labour only. The concrete barrier already in place for the M20 Moveable Barrier Project

2024

19/03/24

8/04/24

21

£ 250,000

20km full movement of concrete barrier & Traffic Management set up and labour

2024

25/05/24

2/06/24

9

£ 250,000

20km full movement of concrete barrier & Traffic Management set up and labour

Total

£ 2,745,000

 

Documents

There are no documents for this release.

This is National Highways' response to a freedom of information (FOI) or environmental information regulations (EIR) request.

You can browse our other responses or make a new FOI request.