Closure of M20 & Operation Brock
Case reference FOI2024/00121
Received 4 April 2024
Published 16 May 2025
Request
I would like to know how much money has been spent in total since the start of the Operation Brock work in 2018, my file of papers shows that the original name for the project at that time was 'M20 Temporary Solution'.
I would also like to know how much it costs taxpayers to put Operation Brock in place and remove it again.
Response
Please see information below:
Year |
Start Date |
End Date |
Date Active |
Conbined Cost to Activate /Deactivate
|
Cost Comment
|
2019 |
24/03/2019 |
18/04/2019 |
25 |
£795,000 |
23km Steel barrier installation & removal Traffic Management set up and labour |
2020/2021 |
28/12/2020 |
28/04/2021 |
121 |
£250,000 |
20km full movement of concrete barrier & Traffic Management set up and labour |
2021 |
17/07/2021 |
01/08/2021 |
15 |
£250,000 |
|
2022 |
22/03/2022 |
06/06/2022 |
76 |
£175,000 |
Traffic Management set up and labour only. The concrete barrier already in place for the M20 Moveable Barrier Project |
2022 |
11/07/2022 |
04/09/2022 |
55 |
£175,000 |
|
2022 |
17/12/2022 |
07/01/2023 |
20 |
£175,000 |
|
2023 |
26/05/2023 |
05/06/2023 |
10 |
£250,000 |
20km full movement of concrete barrier & Traffic Management set up and labour |
2023 |
14/07/2023 |
20/08/2023 |
40 |
£175,000 |
Traffic Management set up and labour only. The concrete barrier already in place for the M20 Moveable Barrier Project |
2024 |
19/03/2024 |
19/03/2023 |
21 |
£250,000 |
20km full movement of concrete barrier & Traffic Management set up and labour |
2024 |
25/05/2024 |
02/06/2024 |
9 |
£250,000 |
|
Total |
|
|
|
£2,745,000 |
|
The scheme costs associated with M20 MB which commenced January 2020 is up to 31 March 2024 is £37,728,475.13.