FOI release

Closure of M20 & Operation Brock

Case reference FOI2024/00121

Received 4 April 2024

Published 16 May 2025

Request

I would like to know how much money has been spent in total since the start of the Operation Brock work in 2018, my file of papers shows that the original name for the project at that time was 'M20 Temporary Solution'.

I would also like to know how much it costs taxpayers to put Operation Brock in place and remove it again.

Response

Please see information below:

 

Year

Start Date

End Date

Date Active

Conbined Cost to Activate /Deactivate

 

Cost Comment

 

2019

24/03/2019

18/04/2019

25

£795,000

23km Steel barrier installation & removal Traffic Management set up and labour

2020/2021

28/12/2020

28/04/2021

121

£250,000

20km full movement of concrete barrier & Traffic Management set up and labour

2021

17/07/2021

01/08/2021

15

£250,000

2022

22/03/2022

06/06/2022

76

£175,000

Traffic Management set up and labour only. The concrete barrier already in place for the M20 Moveable Barrier Project

2022

11/07/2022

04/09/2022

55

£175,000

2022

17/12/2022

07/01/2023

20

£175,000

2023

26/05/2023

05/06/2023

10

£250,000

20km full movement of concrete barrier & Traffic Management set up and labour

2023

14/07/2023

20/08/2023

40

£175,000

Traffic Management set up and labour only. The concrete barrier already in place for the M20 Moveable Barrier Project

2024

19/03/2024

19/03/2023

21

£250,000

20km full movement of concrete barrier & Traffic Management set up and labour

2024

25/05/2024

02/06/2024

9

£250,000

Total

 

 

 

£2,745,000

 

 

The scheme costs associated with M20 MB which commenced January 2020 is up to 31 March 2024 is £37,728,475.13.

Documents

There are no documents for this release.

This is National Highways' response to a freedom of information (FOI) or environmental information regulations (EIR) request.